New Project Alert: Stage 2 for Stapylton

The Q Power electrical team has recently been re-engaged to help complete the second stage of a major industrial construction project in Stapylton on the Gold Coast.

We completed Stage 1 in March last year, working with builders Multi Span Australia Group, where we managed the entire electrical services construction and installation for a new multi-tenancy industrial facility.

Stage 2 involves the (simultaneous!) construction of four additional office and warehouse facilities, which are significantly larger than the one constructed in Stage 1, to meet demand for more industrial and commercial space.

From our team, this next stage calls for incredible efficiency; as Multi Span will construct all four buildings at the same time, our labour and materials forecasts must set us up to maintain optimal productivity in all work areas.

Our Project Manager, Andre, says: “We are extremely grateful to be back on site to deliver Stage 2 with Multi Span and are looking forward to the challenge of delivering all four buildings simultaneously.”

Below are a few snaps of the work in progress!

 

The industrial electrical project site in Stapylton, Gold Coast.

 

The industrial electrical project site in Stapylton, Gold Coast.

 

Q Power Electrical Project Stapylton recap:

The project: Electrical services installation for four new industrial warehouses

Scope of electrical works:

  • MSB alterations
  • Electrical civils
  • NBN civils
  • Cable supports
  • Sub mains
  • Switchboards
  • Energy metering
  • LED lighting
  • Exit and emergency lighting
  • General power
  • Testing and commissioning
  • 12-month DLP

Where: Christensen Rd, Staplyton

When: Now-September 2022

Get in touch with our team today for a chat about your next project and an on-time quote. Or, learn more about our electrical project and gate automation work.

Share this:

One Comment

Leave a Reply

Your email address will not be published. Required fields are marked *